Consider the following statements regarding the Ken-Betwa Link Project:
- It was approved by the Union Cabinet in December 2021 at an official cost of Rs 44,605 crore at 2020-21 price levels.
- It transfers water from the Betwa river in Uttar Pradesh to the Ken basin in Madhya Pradesh via the Daudhan Dam.
- Nearly 2,000 families face displacement from submergence caused by the project.
How many of the above statements are correct?
Tests the ability to catch a reversed directional fact (which basin transfers water to which) embedded among otherwise accurate project details.