Money Is No Longer the Problem: Why Green Energy Corridor Phase-III Will Rise or Fall on Coordination
The Union Cabinet approved the Green Energy Corridor Phase-III on September 30, 2026, committing ₹1,86,405 crore to intra-state transmission and battery storage. The approval follows the curtailment of 8,133 GWh of solar power in April to June 2026. It also follows a December 2025 report of the Parliamentary Standing Committee on Energy that identified right-of-way compensation, land acquisition and clearance delays as the…