Summary
On 13 November 2026, Maharashtra's Forest Department ordered an immediate halt to work on Adani Green Energy's 1,500 MW Tarali Pumped Storage Project in Satara's Patan taluka, because construction had begun without approval from the National Board for Wildlife.
The company says it obtained Environmental Clearance on 11 February 2025 and Consent to Establish on 7 April 2025, after which construction began. It says its wildlife clearance proposal is pending with the NBWL and that no part of the project lies in a notified Protected Area or involves forest land.
Wildlife clearance records place the project in the eco-sensitive zone of the Sahyadri Tiger Reserve, close to Koyna Wildlife Sanctuary. On 17 November, Forest Minister Ganesh Naik met company executives and told them to meet all obligations.
Separately, the State moved to withdraw a letter accepting a cost revision that had cut the conservation deposit from ₹227 crore to ₹2.27 crore. Villagers have also raised concerns about drinking water and water levels.
WHY IT MATTERS FOR UPSC & STATE PCS
Maharashtra's Forest Department halted work on the Tarali Pumped Storage Project on 13 November 2026 because construction had started without NBWL approval. Four days later, the Forest Minister met the developer's executives.
Standard News
The Sequence Is the Safeguard: Where Tarali's Clearance Chain Broke
The rule on paper is clear. A project in the eco-sensitive zone of a protected area needs a decision from the Standing Committee of the National Board for Wildlife before physical work begins. This follows from the Supreme Court's directions in the Goa Foundation case and the Environment Ministry's guidance.
The wildlife clearance is not a formality to be collected along the way. It is the point at which an independent body judges whether the project should proceed in that location at all. The data from Tarali shows how far practice has drifted from that rule.
What Actually Happened Adani Green
Energy says its 1,500 MW Tarali Pumped Storage Project in Satara received Environmental Clearance on 11 February 2025 and Consent to Establish on 7 April 2025 and that construction began after that. Its wildlife clearance proposal is still pending before the NBWL.
On 13 November 2026, about 19 months later, the Maharashtra Forest Department ordered an immediate halt because work had started without NBWL approval. Wildlife clearance records place the project in the eco-sensitive zone of the Sahyadri Tiger Reserve, close to Koyna Wildlife Sanctuary.
The company argues that no part of the project falls in a notified Protected Area and no forest land is involved. That may be true. But the trigger for wildlife clearance is location within an eco-sensitive zone, not the diversion of forest land.
The Link in the Chain That Failed This is not a
failure of rules, funding or ambition. It is a failure of sequencing and enforcement between agencies. The Environmental Clearance under the EIA Notification and the State pollution board's Consent to Establish are separate approvals from the wildlife clearance, issued by different bodies.
Nothing in the process automatically stopped construction from starting on the first two while the third was pending and no agency checked the gap for a year and a half. The consequence is predictable. Once land is dug and money spent, the NBWL is no longer asked whether the project should be built there.
It is asked whether to halt something already under way. That is a fait accompli and it turns an ecological assessment into a cost-benefit argument loaded in favour of what has already been spent. The ministerial meeting on 17 November adds to the risk.
Forest Minister Ganesh Naik told the company to meet all its obligations, which is the right message. Yet a meeting between the regulator's political head and the developer, days after a stop-work order, can easily become the place where a violation is negotiated into a delay.
The separate dispute over a cost revision that cut the conservation deposit from ₹227 crore to ₹2.27 crore, now being withdrawn, shows how much regulatory value can be lost at points that receive no scrutiny.
Green Versus Green What is
working deserves credit. The Forest Department did issue the stop order, the State is withdrawing the letter on the deposit and the Satara Guardian Minister has ordered a review of villagers' complaints about drinking water and water levels.
Pumped storage is also genuinely needed, because India's renewable grid needs large-scale storage to balance solar and wind. But a clean-energy purpose does not exempt a project from process. In green-versus-green conflicts, the clearance sequence is the only mechanism that ensures ecological costs are weighed before they are incurred.
For the examiner, the lesson is that the order in which approvals are granted is itself part of environmental protection.
Quick Facts
Key numbers & takeaways — revise these first
-
The Tarali Pumped Storage Project is a 1,500 MW project of Adani Green Energy in Patan taluka, Satara district, Maharashtra.
-
The Forest Department issued a stop-work order on 13 November 2026 because construction began without National Board for Wildlife approval.
-
The company says it received Environmental Clearance on 11 February 2025 and Consent to Establish on 7 April 2025.
-
Its wildlife clearance proposal is pending before the NBWL.
-
Wildlife clearance records place the project in the eco-sensitive zone of the Sahyadri Tiger Reserve, near Koyna Wildlife Sanctuary.
-
Forest Minister Ganesh Naik met Adani Green executives on 17 November 2026.
-
A cost revision accepted by the PCCF had cut the conservation deposit from ₹227 crore to ₹2.27 crore; the State has moved to withdraw that acceptance.
-
Section 29 of the Wildlife (Protection) Act, 1972 prohibits habitat destruction in a sanctuary without permission.
-
Pumped storage projects pump water uphill when power is cheap and release it through turbines at peak demand.
Connect the dots for your UPSC preparation.
Standard news covers the event. Log in to read our comprehensive analysis and uncover the hidden constitutional, structural, and ethical dimensions of this topic:
A step-by-step map of how Environmental Clearance, Consent to Establish and NBWL clearance are meant to fit together and exactly where Tarali's sequence broke
Why location in an eco-sensitive zone, not forest diversion, triggers wildlife clearance and how the company's defence sidesteps that
The Supreme Court's Alembic ruling of 2020 on ex post facto clearances and what it implies for projects that start before approval
A reform agenda that links approvals digitally so that no construction permit can activate while a wildlife decision is pending