Summary
The National Green Tribunal's Western Zone Bench in Pune, in an interim order dated 26 September 2026, held that the environmental clearance and Coastal Regulation Zone clearance granted on 21 July 2025 for Mormugao Port Trust's project to deepen its approach channel for cape-size vessels shall not be operationalised until the next hearing on 2 November 2026.
Appellants Rupesh Shinkre, Sanjay Redkar and Jayesh Shetgaonkar argued that the project would raise coal and ore handling capacity from 12 MTPA to 42.1 MTPA without assessing dust pollution for more than 1 lakh people living within 2 km or the impact on fishing communities in 10 villages.
The tribunal directed the port to show within two weeks that an IIT Bombay source-apportionment study on Vasco da Gama's air quality had been placed before the Expert Appraisal Committee. It also remarked that several conditions in the clearance appeared to have been copied without relevance.
The project's first clearance, granted in February 2016, was quashed by the NGT in September 2016 for the absence of a mandatory public hearing.
WHY IT MATTERS FOR UPSC & STATE PCS
The NGT's interim stay on Mormugao Port's channel-deepening clearances, reported on 16 October 2026, is the project's second setback before the tribunal after its 2016 clearance was quashed. It raises questions about how India's Expert Appraisal Committees scrutinise site-specific evidence before granting clearance.
Standard News
The Weak Link Is Appraisal, Not Enforcement The EIA Notification, 2006
requires that large projects be cleared only after their specific impacts have been studied and the affected public has been heard. For Mormugao Port's channel-deepening project, the commitment was clear. The record shows two separate appraisal failures, ten years apart.
The record -
February 2016: The Environment Ministry grants environmental clearance to deepen a channel about 9.66 km long and 0.27 km wide and an inner basin of about 0.89 sq km.
- September 2016: The NGT quashes it because the mandatory public hearing had not been held and sends the matter back to the Expert Appraisal Committee. Fresh terms of reference for the EIA are approved the same year.
- 21 July 2025: Environmental and CRZ clearance is granted again.
- 26 September 2026: The NGT's Pune Bench stays the clearance until its next hearing on 2 November. In 2016, a procedural step was skipped entirely. In 2026, the problem is the quality of the appraisal. The tribunal noted that several conditions in the clearance appeared to be copied in without relevance and that the Environment Ministry's counsel could not explain how they got there. It also directed the port to prove, within two weeks, that IIT Bombay's 2021 source-apportionment study on Vasco da Gama's air quality had been placed before the committee. The appellants say it was not.
Why that study matters The deeper channel would let larger cape-size vessels dock and the appellants say coal and ore handling capacity would rise from 12 MTPA to 42.1 MTPA.
Coal and ore dust is the main concern for Vasco, where, according to the appellants, more than 1 lakh people live within 2 km of the project. A source-apportionment study measures how much of the local particulate pollution comes from each source, including port operations.
A committee assessing a large increase in coal handling without considering that evidence would be making its decision on incomplete information. The appellants also raised livelihood concerns. They say fishing communities in 10 villages within the 10-km study area were overlooked and that dredging about 15 million cubic metres of seabed material would damage fish spawning grounds.
What is
working The safeguards are functioning at the review stage. Residents filed an appeal within the NGT Act's time limits and the tribunal examined the record closely. In 2016 it enforced the public hearing requirement. The Goa Coastal Zone Management Authority had also recorded concerns in May 2024 about the effect of dredging on the estuary and marine life.
The stay is interim and the tribunal has not ruled on the merits. The outcome of the 2 November hearing should not be assumed.
Quick Facts
Key numbers & takeaways — revise these first
-
The National Green Tribunal was established under the National Green Tribunal Act, 2010.
-
Under Section 16 of the NGT Act, an appeal against an environmental clearance must be filed within 30 days, extendable by up to 60 days for sufficient cause.
-
The EIA Notification, 2006 requires public consultation for Category A projects, including major port expansions.
-
The CRZ Notification, 2019 regulates capital dredging and disposal of dredged material in coastal areas.
-
The environmental and CRZ clearance for the Mormugao channel-deepening project was granted on 21 July 2025.
-
The appellants say the project would raise coal and ore handling capacity from 12 MTPA to 42.1 MTPA.
-
The dredging is estimated to generate about 15 million cubic metres of material for offshore disposal.
-
IIT Bombay submitted a particulate source-apportionment study on Vasco da Gama's air quality to the Goa State Pollution Control Board in 2021.
-
The NGT will next hear the matter on 2 November 2026.
Connect the dots for your UPSC preparation.
Standard news covers the event. Log in to read our comprehensive analysis and uncover the hidden constitutional, structural, and ethical dimensions of this topic:
The ten-year timeline from the 2016 clearance to the 2026 stay and what each failure reveals about the EIA process.
How copy-pasted conditions and a missing air-quality study point to weak scrutiny at the Expert Appraisal Committee.
Who bears the risk: Vasco's residents near the coal-handling expansion and fishing communities in 10 villages.
A way forward that strengthens appraisal itself rather than relying on the NGT to catch errors after clearance.