Summary
ISRO is aiming to fly the first operational mission of its Small Satellite Launch Vehicle (SSLV) in December 2026, after two successful development flights in February 2023 and August 2024; the first, in August 2022, failed to reach its intended orbit.
ISRO Chairman V. Narayanan said on the sidelines of the India International Space Conclave in Delhi that one ground test of a modified PSLV third stage has been completed and the rocket will be ready to fly after one more.
The changes follow two consecutive PSLV failures linked to the third stage: PSLV-C61 in May 2025 and PSLV-C62 in January 2026. The Indian Express reports that ISRO planned 17 launches for FY 2026-27 and has managed three, one of them the failed PSLV-C62.
The successes were EOS-05 in September and NVS-03 in October, which brought NavIC's navigation service back.
WHY IT MATTERS FOR UPSC & STATE PCS
ISRO is targeting the SSLV's first operational launch in December 2026 while preparing to return the PSLV to flight after a modified third stage was ground-tested on 12 November. The reports highlight a gap between planned and actual launches.
Standard News
A Rocket You Cannot Switch Off Has to Be Built Right the First Time Here is
what is actually happening. Both of the PSLV's recent failures began in its third stage, a solid rocket motor. A solid motor is a casing packed with propellant that, once ignited, burns until it runs out. Unlike a liquid engine, it cannot be throttled down or shut off mid-flight to save the mission.
All its reliability is built in on the ground: in how the propellant is cast, how the casing and nozzle are made and how carefully flaws are found before launch. A firework is a useful comparison: once lit, it burns its course.
The comparison stops at precision. A rocket motor's propellant is shaped so that it produces exactly the thrust profile the trajectory needs, which is why small manufacturing flaws matter so much.
Two Failures, One Stage, Different Causes PSLV-C61 in May 2025
lost pressure in the third-stage combustion chamber during firing. PSLV-C62 in January 2026 developed roll disturbances and drifted off course near the end of the same stage's burn. ISRO says the causes were different each time.
That is what makes the fix hard: the problem was not one defect but the margin for error in how the stage was made and checked. ISRO's response was to tighten design margins, raw-material acceptance, assembly procedures and inspection and to strengthen the nozzle, then to ground-test the modified motor on 12 November.
Chairman V. Narayanan says one more ground test will clear the PSLV to fly.
The Cadence Problem
The cost of that caution shows in the calendar. ISRO's annual report planned 17 launches for FY 2026-27, including at least four PSLV and five SSLV missions, the Indian Express reports. Three have flown and one of them, PSLV-C62, failed.
Each grounded month delays satellites such as the earth-observation craft lost on the two failed PSLVs. The SSLV is ISRO's answer to cadence. It is designed for quick assembly and to carry up to 500 kg to low Earth orbit, the market of small satellites that want a dedicated, on-demand ride.
A launcher becomes operational after two successful development flights, the Indian Express reports. The SSLV had three: the first, in August 2022, failed to reach its intended orbit and the next two succeeded. Its December flight is the first test of whether it can turn that record into a routine service.
Where India Stands
The global benchmark for small launchers is Rocket Lab's Electron, which flies frequently and has suffered occasional failures, each followed by an investigation and a quick return to flight. India is not short of capability.
NVS-03's launch in October restored NavIC's navigation service. India is short of cadence. The lesson of the PSLV is that cadence built on unverified hardware does not last. For GS3, the useful distinction is between a launcher that can fly and one that can fly reliably, month after month.
The SSLV's December mission is a test of the second.
Quick Facts
Key numbers & takeaways — revise these first
-
SSLV: three solid-fuel stages topped by a liquid Velocity Trimming Module; up to 500 kg to a 500 km low Earth orbit.
-
SSLV development flights: D1 on 7 August 2022 (did not reach the intended orbit), D2 on 10 February 2023 (success), D3 on 16 August 2024 (success).
-
SSLV manufacturing technology was transferred to HAL under an agreement signed on 10 September 2025.
-
PSLV-C61 (18 May 2025, EOS-09) failed after a drop in chamber pressure in the third-stage (PS3) solid motor.
-
PSLV-C62 (12 January 2026, EOS-N1 and 15 co-passenger satellites) failed after roll disturbances near the end of the PS3 burn.
-
A modified PS3 motor was ground-tested at Sriharikota on 12 November 2026.
-
NVS-03 was launched on GSLV-F18 on 30 October 2026 and restored NavIC's fourth active satellite.
-
EOS-05 (GISAT-1A) was launched on 3 September 2026.
-
A second launch complex for small launchers is being built at Kulasekarapattinam, Thoothukudi.
-
ISRO Chairman: V. Narayanan.
Connect the dots for your UPSC preparation.
Standard news covers the event. Log in to read our comprehensive analysis and uncover the hidden constitutional, structural, and ethical dimensions of this topic:
A plain-language explanation of solid rocket motors and why their reliability depends entirely on manufacturing and inspection.
How the PSLV-C61 and PSLV-C62 failures differed and what ISRO's redesign of the third stage changes.
What makes the SSLV different, including its Velocity Trimming Module and small-satellite market and why December's flight matters.
Rocket Lab's Electron as a model of how to combine high cadence with structured recovery from failure.