Summary
On 19 October 2026, the Haryana Electricity Regulatory Commission granted Eleven Power Pvt Ltd a 25-year parallel licence to distribute electricity in Gurugram and Nuh, the first private entry into a sector run until now by the state-owned UHBVN and DHBVN.
Power employees began a three-day strike on 22 October and outages hit parts of Gurugram, cutting water and internet in several homes. Chief Minister Nayab Singh Saini said the government stands with the employees and will appeal against the order at the Appellate Tribunal for Electricity.
Energy Minister Anil Vij said the licence was granted over the government's strong opposition.
WHY IT MATTERS FOR UPSC & STATE PCS
Haryana's power employees began a three-day strike on 22 October 2026 against HERC's grant of a parallel distribution licence to Eleven Power for Gurugram and Nuh. The state government publicly backed the employees and said it would seek a stay from APTEL within five to six days and that it was ready to go to the Supreme Court if needed.
Standard News
The Owner Versus the Umpire Start with the
number a private investor will be looking at: Rs 4,716.73 crore. That is the capital Eleven Power plans to spend between FY27 and FY31 on a 25-year licence to distribute power in Gurugram and Nuh. Haryana's independent regulator granted that licence on 19 October 2026 under the sixth proviso to Section 14 of the Electricity Act, which allows more than one distributor in the same area.
Three days later, the state government stood with striking employees and announced an appeal against its own regulator.
Who felt it first Ashish Sardana, 50, in Gurugram's Sector 7, woke on 22 October to a dead inverter, no running water and no internet; his children, preparing for entrance exams, could not study.
Calls to the helpline dropped, officials' phones were off and the linemen were on strike. In Sector 5, the RWA president took calls from people who could not get to work and others who could not work from home. These households are not parties to the licence dispute. They are its first bill.
The mechanism:
why the State's stance matters more than the licence India's electricity law separates three roles:
- policy belongs to the government; - licensing and tariffs belong to an independent State Electricity Regulatory Commission; - appeals go to APTEL. The design gives investors a reason to trust a licence: it comes from a body that does not own the incumbent. Haryana now plays two roles at once. It owns DHBVN, the incumbent discom serving Gurugram and it is the government that says it never invited any application for privatisation and will fight the licence at APTEL and, if needed, the Supreme Court. It also chose not to invoke the Haryana Essential Services Maintenance Act, 1974, which allows strikes in essential services such as power to be prohibited. The message is that the State treats the strike as an ally, not a disruption. That matters for the transmission chain. Private distribution capital prices regulatory risk: the chance that a licence, once granted, is undone by political action. If a regulator's order can be resisted by the owner of the incumbent through strikes and litigation, investors will either demand higher returns or stay away. In this sector, higher returns ultimately show up in tariffs or subsidies and staying away leaves consumers with no choice at all.
Where cross-subsidy fits The State's worry is real.
Gurugram and Nuh generate about 43% of DHBVN's revenue and that money helps subsidise cheaper power for farmers and poorer households. But the law already provides tools: a cross-subsidy surcharge under Section 42 and a universal service obligation under Section 43.
And the State had a route before the order. Section 108 of the Electricity Act lets a state give policy directions to its regulator in the public interest. HERC, for its part, justified the licence by pointing to DHBVN's delays in issuing new connections.
That is a service failure that competition is meant to fix.
For the exam: competition in power distribution depends less on the licence itself than on whether the State, as owner of the incumbent, accepts the umpire's decision.
Quick Facts
Key numbers & takeaways — revise these first
-
Licence: 25-year parallel distribution licence to Eleven Power Pvt Ltd, Gurugram and Nuh, granted by HERC on 19 October 2026 (Case No. PRO-30 of 2026) Significance: First private player in Haryana's power distribution, alongside state-owned UHBVN and DHBVN Planned investment: Rs 4,716.73 crore of capex between FY27 and FY31, with 80% renewable sourcing proposed Legal basis: Sixth proviso to Section 14 of the Electricity Act, 2003 (parallel licences in the same area) Safeguards: Section 42 (open access and cross-subsidy surcharge); Section 43 (universal service obligation) Strike: Began 22 October 2026, for three days; the EEFI said 96% of Gurugram's power staff took part State response: Appeal to APTEL; CM offered to engage the unions' choice of lawyers; district monitoring committees ordered Appeal route: APTEL hears appeals against regulatory commission orders; appeals are filed within 45 days Essential services law: The Haryana Essential Services Maintenance Act, 1974 was not invoked Revenue at stake: Gurugram and Nuh account for about 43% of DHBVN's revenue Precedent: Mumbai, where Tata Power, Adani Electricity and BEST operate overlapping networks
Connect the dots for your UPSC preparation.
Standard news covers the event. Log in to read our comprehensive analysis and uncover the hidden constitutional, structural, and ethical dimensions of this topic:
The full transmission chain from a State's stand against its own regulator to regulatory risk, the cost of capital and the tariffs consumers eventually pay
Why not invoking HESMA, alongside an APTEL appeal and the offer to fund the unions' lawyers, sends a specific signal to private investors
How the Electricity Act's existing tools (the Section 42 surcharge, the Section 43 universal service obligation and Section 108 policy directions) could have addressed the State's concerns before a strike
What Mumbai's parallel licensing and the pending Electricity (Amendment) Bill, 2022 suggest about a durable model for distribution competition
Included in this analysis
Join thousands of aspirants analyzing the news deeply.
Unlock Premium — Rs.699 AnnuallyDon't have an account? Sign up for free